Old Zuari bridge will be made one way for traffic from Panjim to Margao/Vasco
Except very heavy vehicles wt. over 12 tons
New Zuari bridge will also be made one way for traffic from Margao/Vasco to Panaji
Except heavy vehicles it will be both ways
Vehicles over 12 tons from Panaji to Margao/Vasco can use new bridge dedicated lane.
Speed limit 40kmph on new bridge
click here for larger view https://www.flickr.com/photos/joegoaukextra3/24067942211/sizes/o/
Foundation stone was laid by Union Road Transport and Highways Minister Nitin Gadkari
Union Ministers Manohar Parrikar and Shripad Naik, Goa Chief Minister Laxmikant Parsekar and others were present on the occasion
Goa Velha Football ground on 1.1.2016
Rs 2,700 crore cable-stayed parallel bridge over Zuari river in Cortalim - Agassaim.
(Rs.27000,000,000 or $410 millions or £278 Millions)
(3,300 crore as per news in May 2018)
The main bridge will be joined by flyovers / Elevated bypass as follows
1. Bambolim to Agassaim (8.2 kms)
2. Cable stayed bridge 640M and approach roads on both sides ( Total 1.084 kms)
3. Cortalim to Verna (4.3 kms)
https://www.flickr.com/photos/joegoauk73/32879845605/in/photostream/
The bridge will pass over the existing Railway bridge at Cortalim.
Video:
Artistic presentation of 8 lane cable stayed new Zuari bridge .
New bridge design preview
https://www.youtube.com/watch?v=SKaNbbyZW44
Package II - cable stayed bridge and approach roads on both sides (1.084 kms) costing 880.75 cr,
Package III - Cortalim to Verna (4.3 kms) costing Rs 783 cr.
Package IV- is land acquisition, rehabilitation, resettlement – utility shifting and relocation which will cost Rs 264.72 cr, according to PWD Minister Sudin Dhavalikar.
(1 Crore = 100 Lacs or 100,00,000)
Fresh inputs from Toi 5/5/16
8 lane cable stayed bridge 640 mtr long will cost Rs.620 crore
Overall Cost of the project is around 3000 crores
Artistic presentation
https://www.flickr.com/photos/joegoaukextra3/24067942211/
https://www.flickr.com/photos/joegoaukextra3/23522344214/
Bridge completion dates -
Missing / missed targets so far
December 2018 (Minister Nitin Gadkari 9.4.17 election rally) - Missed
March 2019 (Goa Minister Sudin 13.1017) - Missed
April 2019 (as per contract) - Missed
May 2019 - Missed
November 2019 (a reply in Rajya Sabha by minister Mansukh 18.7.17) - Missed
December 2019 - Ready / Inauguration Phase 1, 4 lane say PWD Minister Sudin - Missed
December 2020 - New Chief Minister Pramod Sawant said on 5.6.19, also PWD minister Pauskar 9.12.19 Missed
February 2021 - PWD Minister Deepak Pauskar said on 14.5.2020 - Missed
https://youtu.be/GcfkLy4bAEY
April 2021 - PWD Minister said on 3.6.20 after inspecting drains, fields and slurry at Cortalim Santrant.- Missed
April/May 2021 - PWD Minister Pauskar said Goa Assembly 4.2.2020, also Sept, Oct, Nov, Dec 15, 2020Video 8.8.22 https://youtu.be/T_zSw2Ofzok
Video: 19.7.22
Update: 4.1.2022
50% of cabling work completed i.e. 28 cable set on two towers (4 lanes of the 8) https://youtu.be/II66vvfb2-0
Update: 3.1.2022 Observatory Towers on New Zuari Bridge
Update: 27.12.21
CM of Goa now says the 4 lanes of the 8 will be completed by end of April 2022.
Traffic likely to start on new flyover from Bambolim Siridao, Goa-Velha-Agassaim as from 30th Dec. 2021
Overall cost will go up by Rs.400 crores?
Foundation stone for Viewing Tower with revolving restaurant will be laid soon. RFQ floated.
As of now, about 26 cable sets installed. (Of possible 56 sets)
Update: 22.12.21
Another steel segment lifted and when cable set installed it will be the 26th set (of possible 56 sets)
4.12.21
https://flic.kr/p/2mFXN1a
Segment lifted and anchors ready to take or hold cables on second tower, see pic below
Two more cable sets installed around 21.3.2021
First two sets being November 21, 2020
Riverside pillar towers cable anchors etc
Status same as of 7.4.2021
https://flic.kr/p/2kNHSfH
is completed, 72% of Package II (Main 8 lane cable stayed bridge) is completed and Package III (from Cortalim to Verna) 92% work completed.
1.10.2020
https://www.flickr.com/photos/joegoauk55/50405243626/in/photostream/
10.9.2020
28.8.2020
Update 26.8.20
May 21, 200
Video: Zuari bridge, riverside
Video:
Cortalim Junctions, winged spans etc
https://youtu.be/LGWW5rLxW1k
Pic
https://www.flickr.com/photos/joegoauk49/49909757736/in/dateposted-public/
https://www.flickr.com/photos/joegoauk49/49909234668/in/dateposted-public/
https://www.flickr.com/photos/joegoauk49/49910051177/in/dateposted-public/
May 16, 2020
Video:
Agassaim side riverfront ferry wharf, trains etc
https://youtu.be/nunUFKRplgU
Pics
https://www.flickr.com/photos/joegoauk49/49902430462/in/dateposted-public/
https://www.flickr.com/photos/joegoauk49/49902119696/in/photostream/
https://www.flickr.com/photos/joegoauk49/49902120936/in/photostream/
https://www.flickr.com/photos/joegoauk49/49902119071/in/photostream/
https://www.flickr.com/photos/joegoauk49/49901604668/in/photostream/
Update: May 8, 2020
Cross junction, Cortalim - with side wings spans
https://www.flickr.com/photos/joegoauk43/49871227847/in/dateposted-public/
https://www.flickr.com/photos/joegoauk43/49870924946/in/photostream/
https://www.flickr.com/photos/joegoauk43/49870919611/in/photostream/
Update 05.05.2020
Work was stopped for about 35 days due to nationwide lockdown since 22nd March 2020
Video: 5th May 2020
https://youtu.be/Uo0NsfCUog4
Pics
https://www.flickr.com/photos/joegoauk43/49861356588/in/dateposted-public/
https://www.flickr.com/photos/joegoauk43/49862203797/in/dateposted-public/
https://www.flickr.com/photos/joegoauk43/49862206667/in/dateposted-public/
https://www.flickr.com/photos/joegoauk43/49862208472/in/dateposted-public/
Update 23.2.2020
Both side wings reaches Cortalim Cross Junction
https://www.flickr.com/photos/joegoauk46/49603700277/in/dateposted-public/
https://www.flickr.com/photos/joegoauk43/49861358723/in/dateposted-public/
Goa-Velha bypass
https://www.flickr.com/photos/joegoauk46/49587428953/in/photostream/
Update 06.01.2020
https://youtu.be/UfHj2tckY_0
with entry exit ramp at Cortalim Junction, below railway bridge
Pics
https://www.flickr.com/photos/joegoauk35/49345987546/in/dateposted-public/
https://www.flickr.com/photos/joegoauk35/49345982671/in/photostream/
https://www.flickr.com/photos/joegoauk35/49345982246/in/photostream/
Update 10.12.2019
Video:
Verna - Cortalim - Agassaim - Goa-Velha, Siridao, Bambolim - Panaji
https://www.youtube.com/watch?v=aOkGWXKPn74
https://www.flickr.com/photos/joegoauk34/49199192937/in/dateposted-public/
https://www.flickr.com/photos/joegoauk34/49198496203/in/dateposted-public/
https://www.flickr.com/photos/joegoauk34/49199170682/in/photostream/
https://www.flickr.com/photos/joegoauk34/49199173492/in/photostream/
https://www.flickr.com/photos/joegoauk34/49199191357/in/photostream/
https://www.flickr.com/photos/joegoauk34/49198482218/in/photostream/
Update 9.12.19
New Zuari bridge will be ready by December 2020
PWD Minister Deepak Pauskar also said so far 50% bridge work completed and that of approach roads either sides 70%. Bridge Cost Rs.1,400 crores. H
Update 29.8.19
Video: Cortalim Cross junction to Agassaim Bypass
https://youtu.be/9g4Cz_Irbks
Update: 2.7.2019
Video: Verna Slope to Agassaim
https://youtu.be/TrINw66BVc8
Pictures:
https://www.flickr.com/photos/joegoauk24/48182962746/in/dateposted-public/
https://www.flickr.com/photos/joegoauk24/48182964711/in/dateposted-public/
https://www.flickr.com/photos/joegoauk24/48183031807/in/photostream/
wing spans
https://www.flickr.com/photos/joegoauk24/48183036357/in/photostream/
https://www.flickr.com/photos/joegoauk24/48182951616/in/photostream/
https://www.flickr.com/photos/joegoauk24/48182989561/in/photostream/
https://www.flickr.com/photos/joegoauk24/48183054297/in/photostream/
https://www.flickr.com/photos/joegoauk24/48182993271/in/photostream/
Update: 5.6.2019
The new CM Pramod Sawant says the bridge will be ready by December 2020 and the 60% of the bridge work completed as on date
Update: 21.5.2019
Video: Riverside piers, Agassaim ferry wharf etc
Pictures
Riverside pier
https://www.flickr.com/photos/joegoauk22/47111707634/in/dateposted-public/
https://www.flickr.com/photos/joegoauk22/47901048221/in/photostream/
https://www.flickr.com/photos/joegoauk22/47111699204/in/photostream/
https://www.flickr.com/photos/joegoauk22/47848993462/in/photostream/
https://www.flickr.com/photos/joegoauk22/47901052501/in/photostream/
Goa-velha bypass Road
https://www.flickr.com/photos/joegoauk21/46984539285/in/photostream/
https://www.flickr.com/photos/joegoauk21/46984538355/in/dateposted-public/
Saleri, Goa-Velha, connecting Siridao river creek
https://www.flickr.com/photos/joegoauk21/46984537755/in/photostream/
https://www.flickr.com/photos/joegoauk21/46984546275/in/photostream/
Update 11.4.2019
Video: Cortalim junction to Verna slope
https://www.facebook.com/joegoauk/videos/10161817314660145/
Pics
https://www.flickr.com/photos/joegoauk20/47530921132/in/dateposted-public/
https://www.flickr.com/photos/joegoauk20/40617868623/in/photostream/
Update 3.4.2019
Video
https://www.facebook.com/joegoauk/videos/vb.879355144/10161793356135145/
Pics
https://www.flickr.com/photos/joegoauk19/40575732193/in/dateposted-public/
Update 14.3.2019
Video
https://www.facebook.com/joegoauk/videos/10161710830285145/?l=1556141869479590573
Pics
https://www.flickr.com/photos/joegoauk19/47328030082/in/photostream/
https://www.flickr.com/photos/joegoauk19/46465862445/in/photostream/
https://www.flickr.com/photos/joegoauk19/47380900191/in/photostream/
https://www.flickr.com/photos/joegoauk19/32439320007/in/photostream/
https://www.flickr.com/photos/joegoauk19/40415479293/in/photostream/
Scaffolding / support that was collapse on 13.3.19
https://www.flickr.com/photos/joegoauk19/33504747188/in/dateposted-public/
https://www.flickr.com/photos/joegoauk19/46465879735/in/photostream/
https://www.flickr.com/photos/joegoauk19/33504753178/in/photostream/
https://www.flickr.com/photos/joegoauk19/46657825624/in/photostream/
Update: 4.3.2019
Video
https://www.facebook.com/joegoauk/videos/10161681077110145/?l=2456508734636695309
Pics
https://www.flickr.com/photos/joegoauk19/32354783817/in/dateposted-public/
https://www.flickr.com/photos/joegoauk19/32354785677/in/photostream/
Update: 21.1.2019
Video: Verna-Cortalim slope
https://www.youtube.com/watch?v=bDcTuQWEAsE
Pics
https://www.flickr.com/photos/joegoauk8/46787594812/in/dateposted-public/
https://www.flickr.com/photos/joegoauk8/46114643174/in/dateposted-public/
https://www.flickr.com/photos/joegoauk8/46114599184/in/dateposted-public/
https://www.flickr.com/photos/joegoauk8/46114608214/in/dateposted-public/
https://www.flickr.com/photos/joegoauk8/46114614134/in/dateposted-public/
https://www.flickr.com/photos/joegoauk8/46114631844/in/photostream/
https://www.flickr.com/photos/joegoauk8/46114636854/in/photostream/
Cortalim junction over existing railway bridge
https://www.flickr.com/photos/joegoauk8/46839800361/in/photostream/
https://www.flickr.com/photos/joegoauk8/46114596504/in/photostream/
https://www.flickr.com/photos/joegoauk8/46114653524/in/photostream/
https://www.flickr.com/photos/joegoauk8/45925257895/in/photostream/
Update: 11.12.18 riverside
Video:
Over railway bridge etc
https://www.youtube.com/watch?v=QvtepzdUId4
Pics
https://www.flickr.com/photos/joegoauk5/45359319595/in/dateposted-public/
https://www.flickr.com/photos/joegoauk5/45359319705/in/photostream/
https://www.flickr.com/photos/joegoauk5/45359319875/in/photostream/
https://www.flickr.com/photos/joegoauk5/45359320135/in/photostream/
https://www.flickr.com/photos/joegoauk5/45359319595/in/photostream/
Over Konkan Railway bridge
https://www.flickr.com/photos/joegoauk5/44455074030/in/photostream/
https://www.flickr.com/photos/joegoauk5/46221623952/in/photostream/
https://www.flickr.com/photos/joegoauk5/46221624322/in/photostream/
Cortalim junction
https://www.flickr.com/photos/joegoauk5/46221625292/in/photostream/
Update: 8.11.18 riverside
https://www.flickr.com/photos/joegoauk1/45008349735/in/photostream/
https://www.flickr.com/photos/joegoauk1/30982010887/in/photostream/
https://www.flickr.com/photos/joegoauk1/30981999987/
https://www.flickr.com/photos/joegoauk1/45871307582/in/photostream/
Update 11.10. 2018
Video:
https://www.youtube.com/watch?v=WAlY1WMlq58
Pics
https://www.flickr.com/photos/joegoauk73/44340798465/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/44340797235/in/dateposted-public/
Over existing Railway bridge, Cortalim junction
https://www.flickr.com/photos/joegoauk73/30338915427/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/30338917727/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/30338919867/in/dateposted-public/
Update 10.9.18
https://www.flickr.com/photos/joegoauk73/44634136221/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/43724778485/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/44634132701/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/44634130881/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/44634123671/in/dateposted-public/
Video:
https://www.youtube.com/watch?v=J4hMo46MzgY
Update: 30.8.2018
Video:
https://youtu.be/gV2jo1UcPeM
Pics
https://www.flickr.com/photos/joegoauk73/43457923655/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/42556216540/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/43457933805/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/43457944515/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/42556210900/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/43647631724/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/44363929891/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/44315735352/in/dateposted-public/
Update 18.8.18
Video
Status 18.8.2018 Verna to Cortalim
https://www.youtube.com/watch?v=OAmuU3OkGpw
Update 3.7.18
Riverside work, Cortalim pics and video
https://www.flickr.com/photos/joegoauk73/42469428034/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/42469429504/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/42469438254/in/dateposted-public/
Video:
https://youtu.be/cFdrjcZjfZk
update 30.6.18
Video: A tour from Bambolim Camp to Kesarval Verna
Via Siriao, Goa-Velha, Agassiam, Cortalim Konkan Railways bridge tran, Cortalim Junctions etc
https://youtu.be/qIyt8qfLt-U
Pics
https://www.flickr.com/photos/joegoauk73/29242299478/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/42209846345/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/41303134900/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/41303137320/in/photostream/
https://www.flickr.com/photos/joegoauk73/42209842895/in/photostream/
https://www.flickr.com/photos/joegoauk73/29242299478/in/photostream/
https://www.flickr.com/photos/joegoauk73/41303130350/in/photostream/
Update 9.6.18
Span by Span Precast Segmental Construction, Cortalim Verna side
https://www.flickr.com/photos/joegoauk73/28817421498/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/28817421498/in/photostream/
https://www.flickr.com/photos/joegoauk73/28817389528/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/40881454000/in/photostream/
https://www.flickr.com/photos/joegoauk73/40881452390/in/photostream/
update 3.6.18
https://www.flickr.com/photos/joegoauk73/28666868908/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/42488356972/in/photostream/
https://www.flickr.com/photos/joegoauk73/41817299654/in/photostream/
https://www.flickr.com/photos/joegoauk73/41817302794/in/photostream/
https://www.flickr.com/photos/joegoauk73/27669748407/in/photostream/
https://www.flickr.com/photos/joegoauk73/42488366912/in/photostream/
Video
https://www.youtube.com/watch?v=-xLoecrf51g
Update: 23.5.2018
The bridge likely to have two viewing (Observatories) Towers located on top of the two pillars.
It will have a height of 120 mtres from the pile cap
However, the design of the observatory is in final stage and once finalised it will be sent to
the Centre for approval.
This will also add the to the overall bridge cost.
More than30% of bridge work (overall) completed so far, Goa PWD Minister Sudin said
This (Viewing gallery) could also delay the bridge completion date by another 6 months
16.5.18
Cortalim Verna side
https://www.flickr.com/photos/joegoauk73/40339915570/in/photostream/
https://www.flickr.com/photos/joegoauk73/41426470414/in/photostream/
Span by Span Precast Segmental Construction, Cortalim Verna side
https://www.flickr.com/photos/joegoauk73/40339936000/in/photostream/
https://www.flickr.com/photos/joegoauk73/40339934460/in/photostream/
https://www.flickr.com/photos/joegoauk73/41426467914/in/photostream/
7.5.2018
Cortalim side
Span by Span Precast Segmental Construction, Cortalim Verna side
https://www.flickr.com/photos/joegoauk73/27121142107/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/41271653734/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/41271656714/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/41946007082/in/dateposted-public/
Video 7.5.28
https://youtu.be/kjIYu1aY2ZA
22.4.18
Cortalim towards Verna
Span by Span Precast Segmental Construction, Cortalim Verna side
https://www.flickr.com/photos/joegoauk73/40931809304/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/40931810624/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/40931811774/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/40931806994/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/40931805724/in/dateposted-public/
17.4.18
30% of the bridge work completed as of now, says Goa PWD Minister Sudin Davlikar
On 23.5.18, the minister said 30%+ work completed so far
Today's video:
https://www.youtube.com/watch?v=HcG4rJFkI14
Today's pic
https://www.flickr.com/photos/joegoauk73/40642990815/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/39727237890/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/40824107964/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/40824108954/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/40642984665/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/26667398417/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/26667363427/in/dateposted-public/
30.3.18
cortalim
https://www.flickr.com/photos/joegoauk73/40419767494/in/photostream/
https://www.flickr.com/photos/joegoauk73/27257593758/in/photostream/
https://www.flickr.com/photos/joegoauk73/27257592668/in/photostream/
https://www.flickr.com/photos/joegoauk73/27257591228/in/photostream/
Update 2.2.108
Video: Covering Verna slope Cortalim to Agassaim end Zuari bridge
https://www.youtube.com/watch?v=XFcFJpf5auQ
Pics
https://www.flickr.com/photos/joegoauk73/26198684268/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/40072366831/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/40072369181/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/40072371161/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/39173479805/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/25200276627/in/dateposted-public/
https://www.flickr.com/photos/joegoauk73/39173487295/in/dateposted-public/
Update 16.1.2018
video & pics
https://www.youtube.com/watch?v=K1rO1Lv8H2c
Pics
https://www.flickr.com/photos/joegoauk73/39738489771/in/dateposted/
https://www.flickr.com/photos/joegoauk73/39029500284/in/photostream/
https://www.flickr.com/photos/joegoauk73/39029489994/in/photostream/
Update 9.1.2018
Video: A view from Sancoale
https://youtu.be/PAsgIMJXfMs
Pics
https://www.flickr.com/photos/joegoauk73/39612419311/in/photostream/
https://www.flickr.com/photos/joegoauk73/24744252397/in/photostream/
https://www.flickr.com/photos/joegoauk73/24744237157/in/photostream/
https://www.flickr.com/photos/joegoauk73/38904082514/in/photostream/
https://www.flickr.com/photos/joegoauk73/24744123977/in/photostream/
Cortalim NH17 6.1.2018
https://www.flickr.com/photos/joegoauk73/27765658219/in/photostream
https://www.flickr.com/photos/joegoauk73/38645701055/in/photostream/
https://www.flickr.com/photos/joegoauk73/39542089451/in/photostream/
https://www.flickr.com/photos/joegoauk73/25671362398/in/photostream/
Update 18.12.17
Video
https://www.youtube.com/watch?v=nyQ6E6T3Ujk
Update 16.11.17
Some pics taken from the bridge/from a moving bus
https://www.flickr.com/photos/joegoauk73/38407873546/in/photostream
https://www.flickr.com/photos/joegoauk73/37749148944/in/photostream/
https://www.flickr.com/photos/joegoauk73/38431901772/in/photostream/
https://www.flickr.com/photos/joegoauk73/37577424375/in/photostream/
Cortalim Road
https://www.flickr.com/photos/joegoauk73/24592716388/in/photostream/
https://www.flickr.com/photos/joegoauk73/26688026709/in/photostream/
https://flic.kr/p/21uovnY
https://flic.kr/p/Zu8Zqh
Update Oct 2017
New Zuari bridge ready by March 2019
Says Goa PWD Minister Sudin Davlikar on 13.10.17
NT 14/10/17
In spite of the delay in the ongoing construction of the Zuari bridge due to the changes in sub-structural design, the bridge would be ready in March 2019 as per the schedule.
Coming out with this information, Minister for Public Works Ramakrishna ‘Sudin’ Dhavalikar said that the sub-structural design of the new under-construction Zuari Bridge would have to undergo changes vis-Ã -vis piling foundation.
more details here
http://www.navhindtimes.in/new-zuari-bridge-by-march-2019-as-scheduled/
Update: July/August
Video: Road widening, bridge, flyover road etc Goa-Velha, Agassaim, Cortalim etc
https://youtu.be/Dq2WO5LLp54
Update 12.8.2017
Video: Status as on 12.8.17
https://youtu.be/YllmlmR4V_U
Pictures
https://www.flickr.com/photos/joegoauk73/36383402831/in/photostream
https://www.flickr.com/photos/joegoauk73/36352727232/in/photostream/
https://www.flickr.com/photos/joegoauk73/36352703342/in/photostream/
https://www.flickr.com/photos/joegoauk73/36520839965/in/photostream/
https://www.flickr.com/photos/joegoauk73/35711931213/in/photostream/
https://www.flickr.com/photos/joegoauk73/36520805045/in/photostream/
https://www.flickr.com/photos/joegoauk73/36383288651/in/photostream/
https://www.flickr.com/photos/joegoauk73/35685714984/in/photostream/
https://www.flickr.com/photos/joegoauk73/36383203751/in/photostream/
https://www.flickr.com/photos/joegoauk73/36352533042/in/photostream/
https://www.flickr.com/photos/joegoauk73/35711757613/in/photostream/
https://www.flickr.com/photos/joegoauk73/36383127801/in/photostream/
https://www.flickr.com/photos/joegoauk73/36383085311/in/photostream/
https://www.flickr.com/photos/joegoauk73/35685534944/in/photostream/
https://www.flickr.com/photos/joegoauk73/36383031861/in/photostream/
https://www.flickr.com/photos/joegoauk73/36383007141/in/photostream/
https://www.flickr.com/photos/joegoauk73/36352376152/in/photostream/
https://www.flickr.com/photos/joegoauk73/36123913680/in/photostream/
https://www.flickr.com/photos/joegoauk73/35685688854/in/photostream/
https://www.flickr.com/photos/joegoauk73/36382844631/in/photostream/
Update 18/7/17
New completion date: It is now expected to be completed by November 2019
(Earlier target was May 2019).
Only 1% (one) if the Zuari bridge work completed so far.
It was announced in the Rajya Sabha by the Transport and Highway minister Mansukh
Update: 9.4.2017
Minister for Road Transport/Highways Nitin Gadkari has assured the bridge will be completed by end 2018. He was speaking a a BJP rally held in Campal Goa on 9.4.17
watch video
https://www.youtube.com/watch?v=I-e6OFSyXNM
TOI goa 10.4.17
https://www.flickr.com/photos/joegoauk73/33166059543/in/photostream
https://www.flickr.com/photos/joegoauk73/33849238171/in/photostream
Update 8.2.2017 - Pics and video
Video:
https://www.youtube.com/watch?v=wkvBxUy9DAo
Pics
https://www.flickr.com/photos/joegoauk73/32645026572/in/photostream
https://www.flickr.com/photos/joegoauk73/32645032892/in/photostream/
https://www.flickr.com/photos/joegoauk73/32798163515/in/photostream/
https://www.flickr.com/photos/joegoauk73/32798176695/in/photostream/
https://www.flickr.com/photos/joegoauk73/31955233014/in/photostream/
https://www.flickr.com/photos/joegoauk73/31955239494/in/photostream/
https://www.flickr.com/photos/joegoauk73/32645081332/in/photostream/
https://www.flickr.com/photos/joegoauk73/31984110733/in/photostream/
https://www.flickr.com/photos/joegoauk73/32417908680/in/photostream/
https://www.flickr.com/photos/joegoauk73/32417922970/in/photostream/
https://www.flickr.com/photos/joegoauk73/32645128572/in/photostream/
https://www.flickr.com/photos/joegoauk73/32675266221/in/photostream/
https://www.flickr.com/photos/joegoauk73/32675275421/in/photostream/
https://www.flickr.com/photos/joegoauk73/32417957760/in/photostream/
https://www.flickr.com/photos/joegoauk73/32758034646/in/photostream/
https://www.flickr.com/photos/joegoauk73/32758040106/in/photostream/
https://www.flickr.com/photos/joegoauk73/32675304701/in/photostream/
https://www.flickr.com/photos/joegoauk73/32798283615/in/photostream/
https://www.flickr.com/photos/joegoauk73/32798291345/in/photostream/
https://www.flickr.com/photos/joegoauk73/32758060726/in/photostream/
https://www.flickr.com/photos/joegoauk73/32798308255/in/photostream/
https://www.flickr.com/photos/joegoauk73/32798342305/in/photostream/
https://www.flickr.com/photos/joegoauk73/31984240153/in/photostream/
https://www.flickr.com/photos/joegoauk73/32758109266/in/photostream/
https://www.flickr.com/photos/joegoauk73/31955426104/in/photostream/
https://www.flickr.com/photos/joegoauk73/32798374865/in/photostream/
https://www.flickr.com/photos/joegoauk73/32798382315/in/photostream/
https://www.flickr.com/photos/joegoauk73/32418114160/in/photostream/
https://www.flickr.com/photos/joegoauk73/32758173686/in/photostream/
https://www.flickr.com/photos/joegoauk73/32758180106/in/photostream/
https://www.flickr.com/photos/joegoauk73/31984313913/in/photostream/
https://www.flickr.com/photos/joegoauk73/31984332633/in/photostream/
https://www.flickr.com/photos/joegoauk73/32758208006/in/photostream/
https://www.flickr.com/photos/joegoauk73/32645395342/in/photostream/
https://www.flickr.com/photos/joegoauk73/31984354993/in/photostream/
https://www.flickr.com/photos/joegoauk73/31984369633/in/photostream/
https://www.flickr.com/photos/joegoauk73/31984378813/in/photostream/
https://www.flickr.com/photos/joegoauk73/32675501061/in/photostream/
https://www.flickr.com/photos/joegoauk73/32675511441/in/photostream/
https://www.flickr.com/photos/joegoauk73/31984384783/in/photostream/
https://www.flickr.com/photos/joegoauk73/31984389133/in/photostream/
https://www.flickr.com/photos/joegoauk73/32758283846/in/photostream/
https://www.flickr.com/photos/joegoauk73/32758289546/in/photostream/
https://www.flickr.com/photos/joegoauk73/32758297646/in/photostream/
https://www.flickr.com/photos/joegoauk73/32879832815/in/photostream/
https://www.flickr.com/photos/joegoauk73/32037074814/in/photostream/
https://www.flickr.com/photos/joegoauk73/32065308783/in/photostream/
https://www.flickr.com/photos/joegoauk73/32879783905/in/photostream/
the existing bridge (1983)
https://www.flickr.com/photos/joegoauk73/32645057482/in/photostream/
https://www.flickr.com/photos/joegoauk73/32645065072/in/photostream/
https://www.flickr.com/photos/joegoauk73/32645071402/in/photostream/
https://www.flickr.com/photos/joegoauk73/31984102873/in/photostream/
https://www.flickr.com/photos/joegoauk73/32417950390/in/photostream/
with konkan Railways bridge
https://www.flickr.com/photos/joegoauk73/32645162482/in/photostream/
https://www.flickr.com/photos/joegoauk73/31984210973/in/photostream/
https://www.flickr.com/photos/joegoauk73/31984215393/in/photostream/
https://www.flickr.com/photos/joegoauk73/31984221033/in/photostream/
Update Aug. 8, 2016
New Zuari bridge rady by April 2019 say Road Surface Minister Mansukh Mandaviya in Rajya Sabha on 8.8.16 in written reply to Congress MP Shantaram Naik (Goa). The work will cost Rs.936 crores. To build under EPC (Engineering, Procurement and Construction). Work already awarded in February 15
Update Aug. 2, 2016
Work on new Zuari bridge to start from October 2016 says PWD Minister Sudin in the Assembly House
Update May 24, 2016
Work on new Zuari bridge to start in next 2-3 months
Says PWD Chief Engineer (Officiating) Uttam Parsekar H dtd 25.5.16
Update May 5, 2016 (TOI)*
Work on Construction of the bridge likely to start in 4 months as soil testing etc still going on
Update 23.2.16
Work order issued (around 22.2.16) ?
As the DBL has to carry out it own soil tests etc the actual starting of bridge work could start after 6 months say around August 2016 or later and the new bridge would be ready by August 2019 if it completes within its given deadline period of 3 years.
DBL in joint venture with the Ukraine Company Mostobudivelnyi Zahin Limited
Partly Sourced from TOI 23.2.16
update February 11.2016
Dilip Buildcon Ltd (DBL) of Bhopal (Madhya Pradesh) won the contract to build 640-long 8 lane cable stayed bridge for over 450 (620 crores*). The work will start after the work order issued by Ministry of Road Transport within a month. The other two tenders for approach roads etc will be opened soon.
Old Zuari bridge
The bridge was build by Gammon India Ltd.
Public transport buses started plying on the bridge around 12th May.
Ferry stopped plying on this sector (Except Madkai) around 17th May thus RND losing about 25 lacs per year due to stoppage of ferries on this profitable route. In 70s, all over Goa, every passenger paid 25p to cross river by ferry, vehicles at extra charge. Passengers and two wheeler on ferries now (all Goa) travel free of cost probably since 1986 after the collapse of Mandovi bridge at Panaji.
Bridge Toll booths started collecting toll as from 15th Sept 1983. Toll being Rs.10 for buses/Trucks, Rs.2 for light vehicle, cars and 50p for two wheeler. Toll collection was expected to run for 10 years with yearly income revenue of 55 lacs
For New Mandovi bridge or third Mandovi bridge visit here